Monday, September 5, 2011

pictures from the summer...

 replaced a load-bearing wall with a beam
 pulled out a bunch of concrete
 dug a 90 foot long trench from the road to the house
  and installed a new sewer
 installed insulated skirting between the piers
 rebuilt and skirted all the piers along the front side of the house
 and skirted the previously rebuilt piers on the east side
 then a coat of "quickwall"
 decided to take out the second chimney
 rebuilt the final section of floor
 removed the roof over the front half of the house
built the new bearing wall
 installed ceiling joists
 new ridgeboard
 cut rafters
and we've almost got a roof...

No comments:

Post a Comment